NOV 18

10 de 16 departamentos de Fase I estan terminados con pisos, carpinteria, pintura, muebles de bano y cocinas, listos para entrega a principios de 2019.

En los jardines se estan recibiendo las primeras plantas y la piscina ya esta casi terminada, el edificio de gimnasio, salon de usos multiples y BBQ roof garden sigue avanzando. El estacionamiento ya se tiene techado 1/3 del area total, la cual sirve ademas como cimientos para 3 de las torres de Fase II que iniciara en 2019.

10 out of 16 units of Phase I are ready to be delivered early 2019, the flooring, painting, bathrooms and kitchens were installed this month.

Regarding the amenities, the gardens are starting to receive the first plants, and the pool is almost done, the building hosting the fitness center, lounge room and BBQ roof garden is being completed. One third of the underground parking area has been finished, the ceiling of the parking lot will also be used as the foundation for the Phase II towers, which are now ready to be started in 2019.



Комментарии


bottom of page